Canadian
Engineers preparing canal bridges for demolitionAccording to a field message sent by the commander of the Canadian Engineers,
Lieutenant-Colonel Armstrong, it was confirmed at 9.25pm that his Engineers
were working on the following bridges. They were preparing the bridges for demolition
to prevent the German Army crossing the Yser Canal.
The remaining footbridges known as A. and No. 1 were prepared for demolition by a party of the Canadian 1st Field Company under Regimental Sergeant-Major Ridgewell. 1st Field Company was billeted west of the canal and had been building splinter-proof head-cover at the 1st Canadian Division headquarters at Chateau des Trois Tours near Brielen. The Engineers' headquarters' staff were now guarding these two bridgeheads.
The foot-bridges Nos. 3 and 3A, half a mile nearer to Ypres, and the horse traffic bridge No. 2 were also charged and manned.